STANDARD EQUIPMENT OF A MOBIL BOILER ROOM - GAS WARM-WATER
HEATING PART
expander, safety elements, mixing valve, pumps, fittings
max. operating pressure of 3 bar - condensing boilers
max. operating pressure of 6 bar - cast iron and steel boilers
WATER PART
water softening, automatic re-filling, max. operating pressure of 10 bar
FUEL PART
gas supply to the burner, gas pressure control, fuel emergency lock, fittings, max. input pressure of 4 bar
ELECTRICAL PART
equithermal control, 1 mixing circuit, WSW heating control, lighting, grounding, boiler rooms up to 600 kW - 230 V / 5 kW, boiler rooms over 600 kW - 380 V / 10 kW
OPERATION
sporadic attendance, information on emergency conditions sent via GSM, possibility of remote PC visualization
CONTAINER
thermally insulated, light color, dimensions of approx. 5 to 7 m, height up to 3,3 m, fire resistence for 30 minutes
SMOKE STACK
6 meter high, self supporting, 3 component stack (stainless steel - heat insulation - aluminum) - for overpressure boilers
6 meter high, self supporting, 3 component stack (plastic - heat insulation - aluminum) - for condensing boilers
BOILERS – version 1
170 – 1300 kW - there are always 2 pcs of boilers:
- 170 – 1 020 KW - cast iron ( with overpressure burners ) – producered by BUDERUS
- 1 300 kW - cast iron + steel ( with overpressure burners ) – producered by BUDERUS
BOILERS – version 2
over 1300 kW - there is always 1 pc of a boiler (steel boiler with overpressure burners) – producered by LOOS, BUDERUS
BOILERS – version 3
do 1520 kW - there are 2 to 16 pcs of wall mounted condensing boilers (TURBO) – producered by BUDERUS
DOCUMENTATION
inspection books and proposed operating and maintenance rules are supplied with the boiler room
OPTIONAL EQUIPMENT FOR EXTRA CHARGE
POWERS
type boiler room powers are selected according to the optimal composition of boilers, powers of the boiler rooms can be modified upon request
WSW PREPARATION
WSW preparation rates can be added to a boiler or delivery separately to your needs
RECOMMENDATION
we suggest to solve requirements for higher number of mixing circuits by placement of a distributor inside the building
HEAT GAUGES
the boiler room can be fitted with ultrasound heat gauges for the heat circuit and for the WSW preparation circuit
GAS METERS
the boiler room can be fitted by a gas meter or a gas re-calculator
CUSTOMER REQUIREMENTS
INQUIRY
in case you are interested in our services, send us a written inquiry - questionnaire for mobile boiler rooms
BASE
hard base has to be prepared that is able to bear approx. 5 to 10 tons (panels, ties, concrete footing)
TRANSPORT
we solving a transport and unloading of the boiler room, eventually a customer after the agreement
MEDIA
gas, heating medium, water and power connections to be solved by the customer, eventually we after the agreement
OTHER INFORMATION
RENTALS
have to be agreed individually according to the current usage of rented boiler rooms in the given period
SERVICE
in the Slovak Republic provided by CONUS Group, abroad provided by contractual partners
DELIVERY TIME
10 – 12 weeks (Buderus boilers)
12 – 20 weeks (LOOS boilers)
PROJECT DOCUMENTATION
in the even interest click here to project documentation