STANDARD EQUIPMENT OF MOBIL BOILER ROOMS CONUS - OIL STEAM

HEATING PART

safety elements, steam fittings, max. operating pressure of 8 bar

WATER PART

chemical water treatment, automatic dosing, feed tank and pumps, fittings, max. operating pressure of 10 bar

FUEL PART

oil storage - twin-shell tanks, oil supply to the burner, fuel emergency lock, fittings

ELECTRICAL PART

steam pressure based control, lighting, grounding, boiler rooms up to 600 kW - 230 V / 5 kW, boiler rooms over
600 kW - 380 V / 10 kW

OPERATION

sporadic attendance within 24 hours, information on emergency conditions sent via GSM, possibility of remote PC visualization

CONTAINER - 1 pc

thermally insulated, include a floor, rigid structure with stability for broken terrain, the tonnage is 26 tons, a floor is from laminated bamboo-wood or from steel with nonskud surface, blue color, a stacking 8 pcs, a length from 2 till 13 m, a width from 2 till 3 m, a height from 2 to 3,5 m, the best quality of lacker in worldmarket, fire resistence

SMOKE STACK

4 meter high, self supporting, 3 component stack (stainless steel - heat insulation - aluminum)

BOILERS

there are different types of steam boilers or steam generators, you can find here

DOCUMENTATION

inspection books and proposed operating and maintenance rules are supplied with the boiler room

TECHNICAL CONDITIONS

CONDENSATE

return rate over 50%, temperature over 80°C

SLUDGE BLOW-OFF

automatic operation

SLAG DRAINAGE

automatic operation

WATER

water hardness for the chemical water treatment max 20°d (German grade)

CUSTOMER REQUIREMENTS

INQUIRY

in case you are interested in our services, send us a written inquiry - questionnaire for mobile boiler rooms CONUS

BASE

useful base has to be prepared hard but is it not necessary exactly level surface for our containers with weight approx. 5 till 30 tons - a standard hard level surface is adequate eventually only a concrete, an asphalt, a garth or panels, ties, concrete footing, etc. - it is not necessary a field engineering and it is saving of costs compared to past or to other containers

TRANSPORT

we solving a transport and unloading of the boiler room, eventually a customer after the agreement

MEDIA

oil, heating medium, water and power connections to be solved by the customer, eventually we after the agreement

OTHER INFORMATION

RENTALS

have to be agreed individually according to the current usage of rented boiler rooms in the given period

SERVICE

in the Slovak Republic and in the Czech Republic provided by CONUS Group, abroad provided by contractual partners

DELIVERY TIME

12 – 16 weeks – steam generators: BOSCH, CERTUSS, GARIONI NAVAL, CLAYTON, THERMINDUS 

16 – 20 weeks – steam-boilers: BOSCH, KU

PROJECT DOCUMENTATION

we provide an orientation project documentation for location of mobil boiler room in the event of interest