STEPS TO BE TAKEN BY PERSON INTERESTED IN LEASE

  • PERSON INTERESTED will complete the questionnaire about mobile boiler room CONUS and send it by E-mail
  • EUROCONUS will check its leasing schedule to see if it can accommodate the request of the PERSON INTERESTED
  • EUROCONUS will E-mail an offer (or request rejection) to the PERSON INTERESTED within 3 to 5 days
  • offer is to be valid for 15 days, for which EUROCONUS will make a guaranteed reservation of the subject boiler plant in the time schedule
  • guaranteed reservation of boiler plant expires in 15 days and the PERSON INTERESTED will be informed accordingly by E-mail
  • if the PERSON INTERESTED does not make an agreement within 15 days (or does not at least send a purchase order), EUROCONUS will not further guarantee validity of the offer and will offer the boiler plant to other PERSONS INTERESTED
     

IMPORTANT NOTICE

CAPACITY OF BOILER PLANTS

the boiler plant lease is always to be contracted for specific terms based on available capacity, therefore, it is always required to state the required terms in the enquiry

ADVANCE OF PURCHASE ORDER

we recommend contracting the lease of mobile boiler plants several months in advance, or even a year ahead, as the lease is thoroughly scheduled several months or even several years in advance!!!
 

RENTAL PRICE

THE RENTAL PRICE IS DEPENDENT ON

the selected boiler room type and the rental period

PRICE INFORMATION

we will always provide you with a written offer based on reciept of a questionnaire about mobile boiler room CONUS inquiry, the rental price usually reaches approx. 2 000 € per month, by the largest sources it can be also approx. 15 000 € per month

RENTAL COST IS CALCULATED

from the date when boiler room was set up on its destination place - if boiler room hasn't been used for a full month, the rental cost is calculated proportionally according to the number of days in the incomplete month since the boiler room has been delivered
 

RENTAL CONDITION

THE RENTAL FEE INCLUDES

INSURANCE

insurance of the subject of rental against natural threaths (excl. flood areas)

SERVISE INSPECTION

regular annual boiler room inspection, revision and service

INITIAL COMMISSIONING

the initial commissioning of the subject of rental, operator training

FAULT SERVICE

24/7 in case of fault (unnecessary visits of our technician caused by the customer are subject to a charge)
 

THE RENTAL FEE DOES NOT INCLUDE

BASE PREPARATION

preparation of the base for the boiler room installation

BOILER ROOM CENNECTION

installation and connection of the boiler room to individual media

OPERATION

operation of the subject of rental by an operator

OPERATING MEDIA

media necessary for operation (fuel, electrical power, GSM service for evaluation of fault of the subject of rental etc.)

BOILER ROOM TRANSPORT

transport of boiler room from the place of its actual use, eventually from other place where the boiler room is stored, to a place specified by the customer, where the boiler room will be installed as a subject to rental

LOADING AND UNLOADING OF BOILER ROOM BY CRANES

loading of boiler room by a crane or 2 cranes (according to the size of boiler room) from the place of its original location and unloading of boiler room on the place specified by customer

PROJECT DOCUMENTATION OF THE INSTALLATION OF BOILER ROOM

project documentation of the installation of boiler room is realized according to the valid norms before or during the boiler room construction, based on the local situation, and it is realized by customer at his own costs or, if both sides agreed, by renter at the costs of customer and in close cooperation with customer

ENGINEERING ACTIVITY

engineering activity is realized by customer at his own costs or, if both sides agreed, by renter at the costs of customer and in close cooperation with customer

POSSIBILITY TO PROVIDE RENTAL INCLUDING OPERATING SERVICES

We have by our partner TZB Orlova currently operates a control centre for continuous supervision of operation of thermal, gas and technological devices. These optimal conditions enable us to provide operation and servicing on the highes qualitative level, usually for lower operating costs, at the customer’s site. We are able to provide this service in case of your interest. The price depends on conditions and location of the boiler room. You can indicate your interest in operation of the rented boiler room in the questionnaire.

 


STANDARD EQUIPMENT OF MODERATED PRESSURE MOBIL BOILER ROOMS CONUS MKOD 8000 - GAS STEAM

HEATING PART

safety elements, steam fittings, operating pressure 12,2 bar, heat-delivery surface 189 m2, steam temperature 192 °C

WATER PART

chemical water treatment, automatic dosing, feed tank and pumps, fittings, feed water temperature 105 °C

FUEL PART

gas supply to the burner (natural gas or propane), gas pressure control, fuel emergency lock with gas pressure control RMG 330, fittings, gas pressure behind gas pressure control 5,0 kPa, automatics type KAH - RAY - TMG 740-2, gas equipment mobil boiler room KAH, slot burner RAY - UEN 3 SP-SL, rated power of a burner 5 350 kW, regulable power approximately 1 100 - 5 600 kW ( 1 600 - 8 000 kg steam / hour )

ELECTRICAL PART

steam pressure based control, lighting, 400 V / 230 V / 42 kW

OPERATION

continued attendance, possibility of remote control from control centre and PC visualization by request

CONTAINER - 1 pc

thermally uninsulated, blue color, possibility of own heating with own warm-air furnace, dimensions: length 9,35 till 10 m - width 2,85 m - height 4,75 m, at the transport 3,7 m

SMOKE STACK

smoke stack DN 500 or 600 mm, 3 component stack ( stainless steel - heat insulation - aluminum ), high according at need up until 40 m, eventually steel self contained, approximately like high

BOILER

there is 1 pc of a steam boiler - KAH - BK 8,0 T 80 – with power 8 000 kg steam / hour

DOCUMENTATION

inspection books and proposed operating and maintenance rules are supplied with the boiler room


TECHNICAL CONDITIONS

GAS

gas inlet approximately 90 - 100 kPa

CONDENSATE

return rate over 50%, temperature over 80°C

SLUDGE BLOW-OFF

automatic, eventually manual operation

CUSTOMER REQUIREMENTS

INQUIRY

in case you are interested in our services, send us a written inquiry - questionnaire for mobile boiler rooms CONUS

BASE

useful base has to be prepared hard but is it not necessary exactly level surface for our containers with weight approx. 5 till 30 tons - a standard hard level surface is adequate eventually only a concrete, an asphalt, a garth or panels, ties, concrete footing, etc. - it is not necessary a field engineering and it is saving of costs compared to past or to other containers

TRANSPORT

we solving a transport and unloading of the boiler room, eventually a customer after the agreement

MEDIA

gas, heating medium, water and power connections to be solved by the customer, eventually we after the agreement

OTHER INFORMATION

RENTALS

have to be agreed individually according to the current usage of rented boiler rooms in the given period

SERVICE

in the Slovak Republic and in the Czech Republic provided by CONUS Group, abroad provided by contractual partners

DELIVERY TIME

16 – 20 weeks 

PROJECT DOCUMENTATION

we provide an orientation project documentation for location of mobil boiler room in the event of interest

 

 

 

MOBILE BOILER ROOM CONUS - COAL WARM-WATER - container type
STEEL BOILERS

 

boiler room type power (kW) fuel type of boiler pc
CONUS MKOE 150 150 coal EKO 1
CONUS MKOE 300 300 coal EKO 2


A fuel - a coal or pellets.




 

STANDARD EQUIPMENT OF MOBIL BOILER ROOMS CONUS - COAL WARM-WATER ( for WOOD PELLETS also )

HEATING PART

max. operating pressure of 2 bar, mixing valve, expander, safety elements, pumps, fittings

WATER PART

water softening, automatic re-filling, max. operating pressure of 10 bar

FUEL PART

fuel storage in a one day hopper, automatic worm feeder as part of the boiler

ELECTRICAL PART

equithermal control, 1 mixing circuit, WSW heating control, lighting, grounding, 230 V / 5 kW

OPERATION

sporadic attendance, information on emergency conditions sent via GSM, possibility of remote PC visualization

CONTAINER - 1 pc

thermally insulated, include a floor, rigid structure with stability for broken terrain, the tonnage is 26 tons, a floor is from laminated bamboo-wood or from steel with nonskud surface, blue color, a stacking 8 pcs, a length from 2 till 13 m, a width from 2 till 3 m, a height from 2 to 3,5 m, the best quality of lacker in worldmarket, fire resistence

SMOKE STACK

4 meter high, self supporting, 3 component stack (stainless steel - heat insulation - aluminum)

BOILERS

there are different types of boilers, you can find here, e.g. 2 pcs of steel EKO KOMFORT boilers – these are automatic boilers with a retort burner and automatic fuel dosing ( from a hopper ), with a combustion air fan that supports quality combustions, the boiler complies with strict European emission limits, boiler efficiency of 82 to 86%, max. output temperature of 80°C, the boiler automatically controls the stability of combustion

DOCUMENTATION

inspection books and proposed operating and maintenance rules are supplied with the boiler room


AUTOMATIZATION FEATURES FOR EXTRA CHARGE

COAL CHARGING

individual sollution – e.g. belt conveyors, chutes, etc.

ASH DISCHARGE

individual solution – e.g. by worm conveyor into an enclosed container

HEATING PART

max. operating pressure of 6 barwith a plate heat exchanger

WSW PREPARATION

WSW preparation rates can be added to a boiler or delivery separately to your needs

CUSTOMER REQUIREMENTS

INQUIRY

in case you are interested in our services, send us a written inquiry - questionnaire for mobile boiler rooms CONUS

BASE

useful base has to be prepared hard but is it not necessary exactly level surface for our containers with weight approx. 5 till 30 tons - a standard hard level surface is adequate eventually only a concrete, an asphalt, a garth or panels, ties, concrete footing, etc. - it is not necessary a field engineering and it is saving of costs compared to past or to other containers

TRANSPORT

we solving a transport and unloading of the boiler room, eventually a customer after the agreement

MEDIA

fuel storage, heating medium, water and power connections to be solved by the customer, eventually we after the agreement

OTHER INFORMATION

RENTALS

have to be agreed individually according to the current usage of rented boiler rooms in the given period

SERVICE

in the Slovak Republic and in the Czech republic provided by CONUS Group, abroad provided by contractual partners

DELIVERY TIME

10 – 12 weeks

PROJECT DOCUMENTATION

we provide an orientation project documentation for location of mobil boiler room in the event of interest

 

 

 

 

MOBILE OIL WARM-WATER BOILER ROOM CONUS - container type 
CAST IRON or STEEL BOILERS - 2 pcs, eventually 1 pc
The 2nd boiler is 100% reserve in mobil boiler rooms CONUS MKOOK. The power of mobil boiler rooms for one boiler 
( 2 boilers ) is in table. Double power of one boiler is possible according request.

 

boiler room type power (kW) fuel type of boiler pc
CONUS MKOOA 100 50 (100) oil ACV 50 2
CONUS MKOOK 320  160 (320) oil KTU 160 2
CONUS MKOLB 340 170 (340) oil BUDERUS 170 2
CONUS MKLB 350 350 oil BUDERUS 350 1
CONUS MKOV 460 460 oil VIESSMANN 460 1
CONUS MKOOK 500 250 (500) oil KTU 250 2
CONUS MKOLB 560 280 (560) oil BUDERUS 280 2
CONUS MKLD 750 750 oil De DIETRICH 750 1
CONUS MKOOK 800 400 (800) oil KTU 400 2
CONUS MKOLB 920 460 (920) oil BUDERUS 460 2
CONUS MKOOK 1300 650 ( 1 300) oil KTU 650 2
CONUS MKOB 1300 1 300 oil BUDERUS 1300 1
CONUS MKOLB 1370 685 ( 1 370) oil BUDERUS 685 2
CONUS MKOD 1800 1 800 oil KDVE 1800 1
CONUS MKOLB 1820 910 (1 820) oil BUDERUS 910 2
CONUS MKOOK 2000 1 000 (2 000) oil KTU 1000 2
CONUS MKOLB 2040 1 020 (2 040) oil BUDERUS 1020 2
CONUS MKOL 2500 2 500 oil LOOS 2500 1
CONUS MKOLB 2600 1 300 (2 600) oil BUDERUS 1300 2
CONUS MKOOK 3200 1 600 (3 200) oil KTU 1600 2
CONUS MKOOK 5000 2 500 (5 000) oil KTU 2500 2
CONUS MKOOK 7000 3 500 (7 000) oil KTU 3500 2
CONUS MKOOK 8000 4 000 (8 000) oil KTU 4000 2
CONUS MKOOK 10000 5 000 (10 000) oil KTU 5000 2
CONUS MKOOK 12000 6 000 (12 000) oil KTU 6000 2


One steel boiler is in container CONUS MKOOA, CONUS MKOV, CONUS MKOB and CONUS MKOL.
One cast iron boiler is in container CONUS MKLB and CONUS MKLD.
One steel boiler and one cast iron boiler are in container CONUS MKOLB.
Two steel boilers are in container CONUS MKOOK.


A fuel is a oil or a diesel, after exchange of a burner natural gas or a propane.
 

mk_olej-plyn460kw1 mk_olej350kw3


these mobile boiler rooms CONUS are the boilers and a fuel oil storage together in 1 container now

boiler room type power (kW) fuel type of boiler pc
CONUS MKOOA 100 50 (100) OSC 2000 ACV 50 2
CONUS MKOLB 340 170 (340) OSC 4500 BUDERUS 170 2
CONUS MKLB 350 350 OSC 3000 BUDERUS 350 1
CONUS MKOV 460 460 OSC 2000 VIESSMANN 460 1
CONUS MKOLB 560 280 (560) OSC 4500 BUDERUS 280 2
CONUS MKLD 750 750 OSC 2000 De DIETRICH 750 1
CONUS MKOLB 920 460 (920) OSC 4500 BUDERUS 460 2


OIL STORAGE CONUS OSC WITH BOILER(S) IN 1 CONTAINER

OIL STORAGE CONUS OSC 1000 1 000 litres
OIL STORAGE CONUS OSC 1500 1 500 litres
OIL STORAGE CONUS OSC 2000 2 000 litres
OIL STORAGE CONUS OSC 3000 3 000 litres
OIL STORAGE CONUS OSC 3500 3 500 litres
OIL STORAGE CONUS OSC 4500 4 500 litres

mk_olej350kw1 mk_olej350kw2 mk_olej350kw3

OIL STORAGE WITHOUT BOILER(S) IN 1 SEPARATE OIL CONTAINER CONUS OKC

OIL CONTAINER CONUS OKC 6000 6 000 litres
OIL CONTAINER CONUS OKC 7500 7 500 litres
OIL CONTAINER CONUS OKC 9000 9 000 litres
OIL CONTAINER CONUS OKC 12000 12 000 litres


mk_sklad_oleja_web12000
 

OIL STORAGE - 1 SEPARATE DOUBLE-CUP OIL TANK CONUS ONC FOR A BIG POWER OF BOILERS

nadrz_olej_velky_objem